Access to a power transmission system means that the transmission system is continuously used by energy entities connected thereto for the purpose of power injection/ withdrawal. The access to the power transmission system is a service offered by the Serbian TSO – AD Elektromreža Serbia to the energy entities connected to its transmission system, based on which the company generates revenue. Conditions and method of setting the maximum allowed (cap) revenue to AD Elektromreža Serbia are regulated by the Methodology for Setting Tariff Elements for Pricing Access to and Use of Electricity Transmission System adopted by the Energy Agency of the Republic Serbia. AD EMS refers to this Methodology when proposing transmission access tariff rates. The transmission access charges are subject to the approval of the Energy Agency of the Republic of Serbia. Revenues for providing the service of access to the transmission system are the most significant and most prevailing source of JP EMS incomes.  A transmission access accounting period starts at 7.00 AM of the first calendar day of a month and ends at 7.00 AM of the first calendar day of the following month. Matters related to the transmission access are regulated by a Transmission System Access Contract concluded between AD Elektromreža Srbije and energy entity obliged to pay the access service charges. First implementation of transmission access tariff commenced on January 1, 2008.                                      

                                               

TRANSMISSION ACCESS TARIFF RATES
With a Letter no. 501/2021-D-02/1the Energy Agency’s Council gave its approval to the AD EMS’ Decision on transmission access tariffs on September 24, 2021.
The decision on setting the transmission access tariff rates was published in the RS Official Gazette no. 95/2021 dated Oktober 1, 2021 and these tariff rates apply as of Oktober 1, 2021.
Transmission access charges reflect tariffs established via the Methodology for establishing transmission access charges adopted by the RS Energy Agency’s Council on 26 Sept. 2012 (RS Official Gazette no. 93/12, 123/12, 116/14, 109/15, 98/16 и 99/18, 4/19, 158/20, 71/21, 130/22, 141/22, 5/23).

Таriff Element

Таriff

Unit of Measure

Price (RSD) per unit of measure as of February 1, 2021.

Price (RSD) per unit of measure as of October 1, 2021.

Аctive Power

Chargable demand

kW

53,9973

59,3603

 

Excessive demand

kW

215,9892

237,4412

Аctive Energy

Higher daily tariff rate for active energy

kWh

0,4222

0,4742

 

Lower daily  tariff rate for active energy

kWh

0,2111

0,2371

Reactive Energy

Reactive Energy

kvarh

0,2099

0,2863

 

Excessive reactive energy

kvarh

0,4198

0,5727

 

LINKS TO FILES REGULATING ACCESS TO TRANSMISSION SYSTEM
Consent on Transmission Grid Access Prices (document issued by Energy Regulatory Agency): >>link >>

Energy Regulatory Agency – Reasons for the Decision Consent on Transmission Grid Access Prices >>link >>

Mothodology for the Transmission System Access Price Setting: >>link >>

Model of Contract on Transmission Grid Access between JSC Elektromreža Srbije and entity obliged to pay Grid Access: >link >

Mоdel Contract on access to electricity transmission system for privileged electricity producer: >link >